Technical deployment planning

AI Colocation Power & Cooling Requirements

Size the infrastructure before the GPUs arrive.

A practical guide to GPU server power, heat load, rack circuits, liquid cooling and network planning for AI deployments.

Start with complete system draw

GPU thermal design power is not total server input power. Include CPUs, memory, fans, storage and network switches. Collect manufacturer maximum input specifications and measured sustained draw if available. Size for expected peak workload and agreed redundancy conditions, not just average utilization.

Convert electrical load into heat

Nearly all IT electrical input becomes heat. One kW corresponds to approximately 3,412 BTU per hour. A 25 kW IT load therefore produces about 85,300 BTU/h before additional facility loads. Cooling design must also account for airflow, inlet temperature, redundancy and equipment-specific limits.

Understand electrical distribution

For balanced three-phase loads, real power in kW is approximately √3 × line voltage × current × power factor ÷ 1,000. This is not a circuit-sizing prescription. A qualified engineer must account for continuous-load rules, protection, phase balance and failover requirements.

Air versus liquid cooling

Contained air cooling can work for suitable GPU chassis when airflow and heat rejection are adequate. Liquid-cooled equipment requires compatible supply temperature, flow, pressure, coolant chemistry and distribution equipment. Send the OEM installation guide before ordering or shipping rack-scale hardware.

Planning at a glance

IT loadHeat output (BTU/h)Energy at constant load, 30 days
10 kW34,1207,200 kWh
25 kW85,30018,000 kWh
50 kW170,60036,000 kWh
100 kW341,20072,000 kWh

Planning examples only. Confirm equipment requirements and available capacity with Netsonic.

Bring your own GPUs to Netsonic

Our Green Bay facility focuses on 10–100+ kW customer-owned AI deployments. High-amperage circuits, contained air and liquid-ready options, carrier-neutral networking and local 24/7 technicians support a deployment engineered around your equipment.

Explore Netsonic AI colocation →

Frequently asked questions

Is GPU TDP enough to size power?

No. Use complete system input specifications and workload measurements.

Does the table include cooling electricity?

No. It describes IT load only, not total facility energy.

What should I send for a quote?

Server models, quantities, input power, rack dimensions, cooling specifications, network needs and deployment date.

AI colocation planning resources

Let’s plan your GPU deployment.

Send your GPU model, server count, target power and timeline. We will review the power, cooling and network requirements.

Request your quote →

920-432-0360 · [email protected]

-->